CACI No. VF-4510. Breach of Implied Covenant to Perform Work in a Good and Competent Manner - Affirmative Defense - Contractor Followed Plans and Specifications

Judicial Council of California Civil Jury Instructions (2023 edition)

Download PDF
Bgc7f
VF-4510.Breach of Implied Covenant to Perform Work in a Good
and Competent Manner - Affirmative Defense - Contractor
Followed Plans and Specifications
We answer the questions submitted to us as follows:
1. Did [name of defendant] fail to [specify alleged defect in the work
and/or deficiency in performance]?
1. Yes No
1. If your answer to question 1 is yes, then answer question 2. If you
answered no, stop here, answer no further questions, and have
the presiding juror sign and date this form.
2. Was [name of plaintiff] harmed by [name of defendant]’s failure?
2. Yes No
2. If your answer to question 2 is yes, then answer question 3. If you
answered no, stop here, answer no further questions, and have
the presiding juror sign and date this form.
3. Did [name of plaintiff] provide [name of defendant] with the plans
and specifications for the project?
3. Yes No
3. If your answer to question 3 is yes, then answer question 4. If you
answered no, skip questions 4, 5, and 6 and answer question 7.
4. Did [name of plaintiff] require [name of defendant] to follow the
plans and specifications in constructing the project?
4. Yes No
4. If your answer to question 4 is yes, then answer question 5. If you
answered no, skip questions 5 and 6 and answer question 7.
5. Did [name of defendant] substantially comply with the plans and
specifications?
5. Yes No
5. If your answer to question 5 is yes, then answer question 6. If you
answered no, skip question 6 and answer question 7.
6. Was [specify alleged defect in the work and/or deficiency in
performance] because of [name of defendant]’s use of the plans and
specifications?
6. Yes No
1345
Bgc80
6. If your answer to question 6 is yes, stop here, answer no further
questions, and have the presiding juror sign and date this form.
If you answered no, answer question 7.
7. What are [name of plaintiff]’s damages? $
Signed: Presiding Juror
Dated:
After [this verdict form has/all verdict forms have] been signed, notify
the [clerk/bailiff/court attendant] that you are ready to present your
verdict in the courtroom.
New December 2015
Directions for Use
This verdict form is based on CACI No. 4510, Breach of Implied Covenant to
Perform Work in a Good and Competent Manner - Essential Factual Elements, and
CACI No. 4511, Affırmative Defense - Contractor Followed Plans and
Specifications. Questions 3-6 address the affirmative defense.
The special verdict forms in this section are intended only as models. They may
need to be modified depending on the facts of the case.
If different categories or items of damages are claimed, expand question 7 so that
the jury can state a separate amount for each category. (See CACI Nos. 4530-4532,
Owners Damages.) In this way, should a reviewing court determine that a particular
item of damages is not recoverable, it can reduce the judgment by the amount
awarded for that item rather than have to send the case back for a retrial of
damages.
If there are multiple causes of action, users may wish to combine the individual
forms into one form. If different damages are recoverable on different causes of
action, replace the damages tables in all of the verdict forms with CACI No. VF-
3920, Damages on Multiple Legal Theories.
VF-4511-VF-4519. Reserved for Future Use
VF-4510 CONSTRUCTION LAW
1346

© Judicial Council of California.